|
Project Timeline
The US 68/KY 80 project begun in the
early 1990s. The entire project is not supposed to be completed
until at least 2015, over 20 years after the first public meeting.
This is largely due to the lack of federal and state funds over the past
two decades. The timeline below shows target dates of funding and
construction costs and how they have changed significantly over the
years.
February 1992
- Design for the Murray-Aurora
section was included in the state's Six-Year Highway Plan for fiscal
year 1997. Money was allocated for design and construction for
portions of US 68/KY 80 through western Trigg county and in the Land
Between The Lakes.
September 1993
- Public meeting in Murray to
present three alternative routes for the new KY 80 through
Calloway/Marshall counties. Southernmost route chosen.
January 1994
- A total of 45.5 million was
allocated for the design and construction of KY 80 from Murray to
Aurora in fiscal year 1999. Design funds are allocated for
fiscal 1996 for the Kentucky Lake & Barkley Lake bridges.
June 1996
- Murray-Aurora KY 80 portion
broken up into three segments with funds for construction set aside
for fiscal 2000 and 2001.
- Final design funds are
allocated for fiscal 1997 for Mayfield-Murray section. Some
construction funds for this section allocated in fiscal 2001.
- More design funds allocated
for Kentucky Lake bridge in 1996.
- $31 million is allocated for
the construction of the Lake Barkley bridge in fiscal 2002. In
addition, various monies allocated for construction of US 68 in LBL
and west of Cadiz. In fact, construction should have begun on
portions of US 68 west of Cadiz in 1999 and in LBL in 2001.
February 1998
- Construction dates are slated
for 2000 and 2001 for various sections of KY 80 between Murray and
Aurora.
- Construction slated for
2003-2004 for Murray-Mayfield section of KY 80.
- About $7 million is set aside
for the construction of a new bridge over Kentucky Lake in fiscal
2004.
- Construction funds still in
place for portions of US 68 west of Cadiz. Construction should
have begun in 2000.
- Some funds are allocated for
the Lake Barkley bridge in 2003-2004.
- Construction funds are still
allocated for the three segments of KY 80 from Murray to Aurora
between 2000 and 2002.
1999-2000
- The Tennessee Valley
Authority transfers control of the Land Between The Lakes to the US
Forest Service. Studies and designs of the corridor through
LBL are scrutinized and subsequently delays the project.
2001-2002
- Uncertain about exactly when
it happened, but the first section of KY 80 opened in Aurora, about
a half-mile stretch that replaced KY 94. A new entrance to
Kenlake State Park was created. The new construction was from
the intersection of US 68 to the new intersection of KY 94.
This section was constructed quickly, especially considering how
much dirt was moved.
October 2002
- A six-mile section of KY 80
between Murray and Elm Grove opens. An article refers to the
completion of the entire Mayfield to Murray section by Spring 2004.
August 2002
- More designs funds are in
place for the Kentucky Lake bridge in fiscal 2004. Estimate
construction cost is $72 million.
- All phases of US 68
construction between Lake Barkley and Cadiz had construction funds
allocated for 2008.
- Some money for construction
of Lake Barkley's new bridge is allocated in 2007 and 2008.
February 2004
- More funding for construction
of KY 80 in from Murray to Mayfield is allocated for fiscal 2006.
- Kentucky Lake bridge funding
estimated at $72 million; funds allocated for fiscal 2008, 2009, and
2010 for the entire project.
- Lake Barkley bridge funding
estimated at $61 million; funds allocated for fiscal 2007, 2008, and
2009.
- Sections of US 68 through LBL
to Cadiz are slated for construction funding for 2005 through 2010.
October 2004
- An eight-mile section of KY
80 between Elm Grove and Aurora is opened. The road is now
complete between Murray and Aurora.
December 2005
- A public meeting is held at
Kenlake State Park on the plans to four-lane US 68 through the Land
Between the Lakes. For the first time, the public gets a
detailed look of the project (sans the bridges).
October 2006
- Kentucky Governor Ernie
Fletcher announced the expediting of the construction of US 68/KY 80
through LBL in a "design/build" project. $300 million is
allocated for the entire project including two new bridges over the
lakes. A new firm for designing the bridges is hired and the
process finally begins.
July 2007
- The public was invited to get
a glimpse of 24 different bridge designs for Kentucky & Barkley
Lakes. The meeting was held at Lake Barkley State Park.
September 2007
- After years of funding issues
and some "red tape," dirt is turned on the LBL portion of the US 68
project with a scheduled completion of 2009 or 2010.
October 2007
- Another public meeting was
held at Kenlake State Park which showcased nine of the original 24
bridge concepts. The selection was narrowed down to nine and
presented to the public.
February 2008
- An announcement was made that
the nine original concepts for new bridges had been narrowed down to
four. The next public meeting was scheduled for June 2008.
- Design funds of $2 million
are set aside for Kentucky Lake's new bridge. Bridge is now
estimated to cost $170 million, more than double the previous
estimates. Construction is slated for 2012.
- Lake Barkley's new bridge is
now estimated at $120 million. Construction slated or 2011.
In previous plans, bridge construction was supposed to begin around
2002.
- US 68 from Lake Barkley to
Cadiz now as estimated construction date of 2013. At one time,
construction was scheduled to begin 14 years prior.
- Final surfacing construction
for KY 80 from Murray to Mayfield is slated for fiscal 2010.
June 2008
- The final public meeting
scheduled for June 12th for input on bridge design was postponed due
to revised cost estimates of the bridges. A new cost estimate
pegged the two bridges at $540 million which would delay the project
for many years. The design team is meeting to scale back the
designs and will reschedule the final public meeting in the next few
months.
- The portion of KY 80 between
Coldwater and Brinn Road (about one mile west of US 641) will become
a "super-two" highway. Although grade and drain work was
completed for a four-lane highway, only two lanes will be used
between Coldwater and Brinn Road. This is exclusively due to
budget cuts, but it is supposed to be temporary. The
"super-two" highway paving should begin this fall. The other
two lanes' completion date is yet to be determined. The small
section between Brinn Road and US 641 will be four-lanes and should
be completed in the next few months. It should be noted here
for future reference that the state is experiencing extremely
difficult economic times as is the rest of the nation.
August 2008
- Kentucky Governor Steve
Beshear announces at the Murray-Calloway County Chamber of Commerce
that he instructed transportation cabinet officials to find money to
complete the four-lane highway between Murray and Coldwater.
Plans for the super-two were scrapped and the four-lane highway is
scheduled to be completed late next year.
November 2008
- After several months of
postponement, the final public meeting for the Lake Bridges project
will be November 20th at 6:00 p.m. at Lake Barkley State Resort Park
Sources:
Fiscal
1993-1998 Kentucky Six-Year Highway Plan
Fiscal 1995-2000 Kentucky Six-Year Highway Plan
Fiscal 1997-2002 Kentucky Six-Year Highway Plan
Fiscal 1999-2004 Kentucky Six-Year Highway Plan
Fiscal 2001-2006 Kentucky Six-Year Highway Plan
Fiscal 2003-2008 Kentucky Six-Year Highway Plan
Fiscal
2005-2010 Kentucky Six-Year Highway Plan
Recommended Fiscal 2008-2014 Kentucky Six-Year Highway Plan
www.lakebridges.com
|