|
US 68 Lake Bridges Project |
|
|
|
|
 |
|
 |
|
Project Timeline - Nearly 20 Years
in the Making The US
68/KY 80 project begun in the early 1990s. The
entire project is not supposed to be completed until at
least 2015, over 20 years after the first public
meeting. This is largely due to the lack of
federal and state funds over the past two decades.
The timeline below shows target dates of funding and
construction costs and how they have changed
significantly over the years.
February 1992
- Design for the
Murray-Aurora section was included in the state's
Six-Year Highway Plan for fiscal year 1997.
Money was allocated for design and construction for
portions of US 68/KY 80 through western Trigg county
and in the Land Between The Lakes.
September 1993
- Public meeting in Murray
to present three alternative routes for the new KY
80 through Calloway/Marshall counties.
Southernmost route chosen.
January 1994
- A total of 45.5 million was allocated for the
design and construction of KY 80 from Murray to
Aurora in fiscal year 1999.
- Design funds are allocated for fiscal 1996 for
the Kentucky Lake & Barkley Lake bridges.
June 1996
- Murray-Aurora KY 80 portion broken up into three
segments with funds for construction set aside for
fiscal 2000 and 2001.
- Final design funds are allocated for fiscal 1997
for Mayfield-Murray section. Some construction
funds for this section allocated in fiscal 2001.
- More design funds allocated for Kentucky Lake
bridge in 1996.
- $31 million is allocated for the construction of
the Lake Barkley bridge in fiscal 2002. In
addition, various monies allocated for construction
of US 68 in LBL and west of Cadiz. In fact,
construction should have begun on portions of US 68
west of Cadiz in 1999 and in LBL in 2001.
February 1998
- Construction dates are slated
for 2000 and 2001 for various sections of KY 80
between Murray and Aurora.
- Construction slated for
2003-2004 for Murray-Mayfield section of KY 80.
- About $7 million is set aside
for the construction of a new bridge over Kentucky
Lake in fiscal 2004.
- Construction funds still in
place for portions of US 68 west of Cadiz.
Construction should have begun in 2000.
- Some funds are allocated for the
Lake Barkley bridge in 2003-2004.
- Construction funds are
still allocated for the three segments of KY 80 from
Murray to Aurora between 2000 and 2002.
1999-2000
- The Tennessee Valley
Authority transfers control of the Land Between The
Lakes to the US Forest Service. Studies and
designs of the corridor through LBL are scrutinized
and subsequently delays the project.
2001-2002
- Uncertain about exactly
when it happened, but the first section of KY 80
opened in Aurora, about a half-mile stretch that
replaced KY 94. A new entrance to Kenlake
State Park was created. The new construction
was from the intersection of US 68 to the new
intersection of KY 94. This section was
constructed quickly, especially considering how much
dirt was moved.
October 2002
- A six-mile section of KY
80 between Murray and Elm Grove opens. An
article refers to the completion of the entire
Mayfield to Murray section by Spring 2004.
August 2002
- More designs funds are in place for the Kentucky
Lake bridge in fiscal 2004. Estimate
construction cost is $72 million.
- All phases of US 68 construction between Lake
Barkley and Cadiz had construction funds allocated
for 2008.
- Some money for construction of Lake Barkley's
new bridge is allocated in 2007 and 2008.
February 2004
-
More funding for construction of
KY 80 in from Murray to Mayfield is allocated for
fiscal 2006.
-
Kentucky Lake bridge funding
estimated at $72 million; funds allocated for fiscal
2008, 2009, and 2010 for the entire project.
-
Lake Barkley bridge funding
estimated at $61 million; funds allocated for fiscal
2007, 2008, and 2009.
-
Sections of US 68 through LBL to
Cadiz are slated for construction funding for 2005
through 2010.
October 2004
- An eight-mile section of
KY 80 between Elm Grove and Aurora is opened.
The road is now complete between Murray and Aurora.
December 2005
- A public meeting is held
at Kenlake State Park on the plans to four-lane US
68 through the Land Between the Lakes. For the
first time, the public gets a detailed look of the
project (sans the bridges).
October 2006
- Kentucky Governor Ernie
Fletcher announced the expediting of the
construction of US 68/KY 80 through LBL in a
"design/build" project. $300 million is
allocated for the entire project including two new
bridges over the lakes. A new firm for
designing the bridges is hired and the process
finally begins.
July 2007
- The public was invited to
get a glimpse of 24 different bridge designs for
Kentucky & Barkley Lakes. The meeting was held
at Lake Barkley State Park.
September 2007
- After years of funding
issues and some "red tape," dirt is turned on the
LBL portion of the US 68 project with a scheduled
completion of 2009 or 2010.
October 2007
- Another public meeting was
held at Kenlake State Park which showcased nine of
the original 24 bridge concepts. The selection
was narrowed down to nine and presented to the
public.
February 2008
- An announcement was made that the nine original
concepts for new bridges had been narrowed down to
four. The next public meeting was scheduled
for June 2008.
- Design funds of $2 million are set aside for
Kentucky Lake's new bridge. Bridge is now
estimated to cost $170 million, more than double the
previous estimates. Construction is slated for
2012.
- Lake Barkley's new bridge is now estimated at
$120 million. Construction slated or 2011.
In previous plans, bridge construction was supposed
to begin around 2002.
- US 68 from Lake Barkley to Cadiz now as
estimated construction date of 2013. At one
time, construction was scheduled to begin 14 years
prior.
- Final surfacing construction for KY 80 from
Murray to Mayfield is slated for fiscal 2010.
June 2008
- The final public meeting scheduled for June 12th
for input on bridge design was postponed due to
revised cost estimates of the bridges. A new
cost estimate pegged the two bridges at $540 million
which would delay the project for many years.
The design team is meeting to scale back the designs
and will reschedule the final public meeting in the
next few months.
- The portion of KY 80 between Coldwater and Brinn
Road (about one mile west of US 641) will become a
"super-two" highway. Although grade and drain
work was completed for a four-lane highway, only two
lanes will be used between Coldwater and Brinn Road.
This is exclusively due to budget cuts, but it is
supposed to be temporary. The "super-two"
highway paving should begin this fall. The
other two lanes' completion date is yet to be
determined. The small section between Brinn
Road and US 641 will be four-lanes and should be
completed in the next few months. It should be
noted here for future reference that the state is
experiencing extremely difficult economic times as
is the rest of the nation.
August 2008
- Kentucky Governor Steve
Beshear announces at the Murray-Calloway County
Chamber of Commerce that he instructed
transportation cabinet officials to find money to
complete the four-lane highway between Murray and
Coldwater. Plans for the super-two were
scrapped and the four-lane highway is scheduled to
be completed late next year.
November 2008
- After several months of
postponement, the final public meeting for the Lake
Bridges project will be November 20th at 6:00 p.m.
at Lake Barkley State Resort Park
May 2009
- Paving contracts were let
for the completion of Kentucky 80 from Brinn Road in
Murray to Coldwater. Expected completion date
is now early 2010. As of now, no new
developments to report on the bridges spanning
Kentucky & Barkley Lakes.
- Construction of US68/KY 80
through LBL is ongoing.
July 2009
- Kentucky Governor Steve
Beshear announced on July 14th at Lake Barkley State
Park the final design of the new bridges across
Kentucky & Barkley Lakes. Click here for details.&
It was also announced this month that traffic will
soon shift off the old US 68 in LBL to the eastbound
lanes of the new US 68 between Kentucky Lake and the
visitor's center. This is supposed to occur in
late July. Further, the entire project through
LBL is supposed to be complete within a few months.
November 2009
- Kentucky 80 between Murray
and Coldwater opens for traffic. Now, the
entire route between Mayfield, Murray and Aurora is
complete, 16 years after the original public
meeting.
November 2010
- The Land Between The Lakes
portion of the new Kentucky 80 opens for traffic.
Sources:
Fiscal
1993-1998 Kentucky Six-Year Highway Plan
Fiscal 1995-2000 Kentucky Six-Year Highway Plan
Fiscal 1997-2002 Kentucky Six-Year Highway Plan
Fiscal 1999-2004 Kentucky Six-Year Highway Plan
Fiscal 2001-2006 Kentucky Six-Year Highway Plan
Fiscal 2003-2008 Kentucky Six-Year Highway Plan
Fiscal
2005-2010 Kentucky Six-Year Highway Plan
Recommended Fiscal 2008-2014 Kentucky Six-Year Highway Plan
www.lakebridges.com
|
 |
|
 |
|